Maintenance

Planning a shutdown: the parts checklist

A successful shutdown is prepared weeks in advance. A method and a checklist of the parts to order for a desalination plant, a mine or a food-processing line.

By the Nex-Parts technical team 2 min read

A planned shutdown is the chance to overhaul what cannot be fixed during production. But a single missing part can extend the shutdown by several days. The key: prepare the parts list early enough and have it quoted in one go.

1. Start from the records, not from memory

Begin by gathering:

  • the work done since the last shutdown (failures, temporary repairs);
  • monitoring records: pressures, vibration, temperatures, observed leaks;
  • manufacturers’ recommendations (running hours, replacement intervals);
  • feedback from the field teams, who know which machines are “struggling”.

2. Rank equipment by criticality

Not all equipment deserves the same attention. Sort it into three groups: equipment whose failure stops production (high-pressure pumps, main isolation valves, drive motors), equipment that degrades it, and equipment with no immediate effect. The first group must have all its parts on site before the shutdown starts.

3. The checklist of parts to anticipate

Pumps

  • mechanical seals or cartridges;
  • bearings, gaskets, coupling elements;
  • wear rings and shaft sleeves for the pumps being overhauled.

Valves and actuators

  • repair kits (seats, liners, stem seals);
  • actuator seal kits, spare solenoid valves and limit switch boxes;
  • complete valves for positions too worn to repair.

Joints and piping

  • flange gaskets (spiral wound, flat) for every flange opened;
  • new fasteners in the right grade (A4 in marine environments);
  • repair fittings and HDPE fittings if needed.

Electrical and instrumentation

  • transmitters and sensors to recalibrate or replace;
  • heating elements and thermostats;
  • a standby motor for critical drives.

Consumables

  • lubricants (greases and oils) suited to each application, including food-grade options in the food industry;
  • anti-seize compound, cleaning products, small consumables.

4. Anticipate lead times

Standard parts are found quickly; specific parts (large sizes, special materials such as super duplex, seals made to drawing) can take several weeks, especially when imported. Request prices as soon as the shutdown date is known and have delivery times confirmed in writing.

5. One clear list, one single offer

To make quoting easier and avoid mistakes, structure your list with, on each line: the equipment concerned, the manufacturer reference (or a nameplate photo), the quantity and the date needed. A simple Excel file is enough. A single supplier able to quote everything saves you time on consolidation and delivery follow-up.

6. After the shutdown

Record what was replaced, the condition of the removed parts and the parts that were missing. This feedback is the best basis for planning the next shutdown and adjusting your safety stock.

Need a part or a technical opinion? Send us your reference, a nameplate photo or your parts list through our quote request form or on WhatsApp at +212 674 631 270: we reply within 48 working hours.

Related ranges

Maintenance & repair 06 Maintenance & repair View range Pumps & hydraulics 03 Pumps & hydraulics View range Industrial valves 01 Industrial valves View range

Need this part? Request a quote

Send your parts list or a nameplate photo: we come back to you within 48 working hours with a priced offer.

Further reading